Compliance requirements
A bidder must be excluded if it has outstanding national tax, payment or environmental charge debt within the meaning of the Estonian Taxation Act, or tax or social security contribution arrears under the law of its country of establishment.
The contracting authority may also exclude a bidder that has materially or repeatedly breached essential terms of a previous public contract, where this resulted in early termination or cancellation of the contract, a price reduction, compensation for damage or a contractual penalty.
Qualification criteria and exclusion grounds
The bidder must submit a project organisation chart identifying the key experts and their roles. The project manager and/or the owner’s supervision lead may also cover one key expert role, provided they can ensure the required quality in both positions. The experts must take part personally in contract performance and be independent of the construction contractor; any conflict of interest must be reported immediately, and the affected person replaced if requested by the contracting authority.
The project manager must hold either a Level 7 chartered building engineer qualification, specialising in building construction with competence in construction management, or a Level 8 authorised water supply and sewerage engineer qualification, specialising in external water supply and sewerage with competence in construction management. In the last 10 years, the project manager must have completed at least two contracts as project manager for construction or reconstruction of a main technological stage of a water or wastewater treatment plant or an industrial production plant with a capacity of at least 20,000 m³/day. The work must have been completed and handed over to the client.
The owner’s supervision lead must hold either a Level 7 chartered building engineer qualification, specialising in building construction with competence in owner’s supervision, or a Level 8 authorised water supply and sewerage engineer qualification, specialising in external water supply and sewerage with competence in owner’s supervision. In the last 10 years, the lead must have carried out owner’s supervision on at least two contracts involving the commissioning and adjustment of equipment and/or a technological installation forming part of a main technological stage of a water or wastewater treatment plant or an industrial production plant with a capacity of at least 10,000 m³/day.
The water technology owner’s supervision expert must hold a Level 8 authorised water supply and sewerage engineer qualification, specialising in external water supply and sewerage with competence in owner’s supervision. In the last 10 years, this expert must have carried out owner’s supervision on at least two contracts involving the commissioning and adjustment of equipment and/or a technological installation forming part of a main technological stage of a water or wastewater treatment plant or an industrial production plant with a capacity of at least 10,000 m³/day.
The general construction owner’s supervision expert must hold a Level 7 chartered building engineer qualification, specialising in building construction with competence in owner’s supervision. In the last 10 years, the expert must have carried out owner’s supervision on at least two contracts for construction or reconstruction of a main technological stage of a water or wastewater treatment plant or an industrial production plant.
The building electrical installations owner’s supervision expert must hold a Level 7 chartered electrical engineer qualification, specialising in building electrical installations, with competence in their construction and operation. In the last 10 years, the expert must have carried out owner’s supervision on at least two contracts for construction or reconstruction of a main technological stage of a water or wastewater treatment plant or an industrial production plant. For each expert, submit sufficiently detailed information to demonstrate compliance with the relevant requirements.
Before submitting a bid, the bidder must have signed a confidentiality agreement with the contracting authority. The agreement must be completed with the project participant’s details and signed by an authorised representative, then sent through the procurement information exchange, together with the email address of the person who needs access to the project documentation.
The bid price must follow the prescribed structure, with all marked fields completed, and cover all costs of contract performance. The bidder must confirm compliance with the tender documents; where an equivalent solution is offered, its equivalence must be explained and supported by evidence. The notice documents provided do not state the award scoring or detailed evaluation method.
For a joint bid, the joint bidders must appoint an authorised representative from among themselves and include a power of attorney signed by all joint bidders. The bidder must also confirm that it will not involve, for more than 10% of the contract value, subcontractors or suppliers that are Russian nationals, residents or established in Russia; are more than 50% directly or indirectly owned by such persons or entities; or act on their behalf or under their instructions.