Tender detail
Design and construction of the Poiares wastewater treatment plant infrastructure
Summary
The Municipality of Ponte de Lima is procuring the design and construction of a new wastewater treatment plant and associated infrastructure in Poiares, Portugal, as a single, unloted contract. The facility is designed for 4,050 population equivalents, with biological treatment capacity of 600 m³ per day and a peak flow of 60 m³ per hour. The works include MBR treatment, sludge handling, treated-water reuse, photovoltaic generation for on-site use, commissioning and entry into service, with a 720-day overall delivery period.
More tender information after sign-in
The public view shows key tender details. Sign in to open official links, documents and AI tender support.