Die Autobahn GmbH des Bundes is replacing the BW50 bridge carrying the A3 over the A93 near Regensburg. The main works include demolishing the existing four-part structure and constructing its replacement, along with restoring the affected A3 and A93 carriageways, parallel carriageways and ramps, and modifying drainage. The replacement bridge is approximately 5,042 m²; the main works are scheduled from January 2027 to April 2031. Long-term traffic management is procured separately as Lot B.

Reference number
cd71ef2f-85fd-47ab-a10a-d57b7a6c4d9c
Buyer
Die Autobahn GmbH des Bundes - NL Südbayern
Country
Germany (DEU)
Procedure
Open procedure
CPV
45000000 Construction work
Deadline
2026-10-28
Status
Open
Contract subject
Works
Estimated value
Not published