Tender detail
Lhota Rapotina Quarry Site Infrastructure for a New Processing Line
Summary
The contract covers construction of site infrastructure for a new processing line at the Lhota Rapotina quarry: an internal road, a well connection, a wastewater treatment plant and sewerage, as well as facilities, a workshop and warehouses. The estimated contract value is CZK 60,000,000, and the planned delivery period is 16 April 2027 to 31 August 2028. This is a restricted procedure; applications to participate must be submitted electronically by 12:00 on 9 November 2026. Price is the only award criterion. Bidders must provide evidence of a CZK 1,000,000 tender guarantee with their bid.
More tender information after sign-in
The public view shows key tender details. Sign in to open official links, documents and AI tender support.