Pannon-Víz trenchless rehabilitation works 2026–2027
Summary
Pannon-Víz is procuring trenchless rehabilitation works for drinking-water and wastewater pipelines in two lots, with excavation kept to a minimum. Lot 1 covers 2,692 m across five sites in Győr: 490 m of drinking-water pipes and 2,202 m of wastewater pipes, using epoxy-resin liners. Lot 2 covers works at three sites in Páli and Csorna, including pipeline lining and rehabilitation, replacement of four valves and renovation of 16 inspection chambers; the notice states a total length of 435.4 m. The works are to be completed within 12 months of the contract taking effect.