Water supply, sewerage and stormwater systems of Velvento Municipality
Summary
The contract covers the complete replacement and construction of the wastewater, stormwater and water-supply networks in Velvento, including manholes, associated civil works, connections to existing facilities, testing, operational equipment locations, and full restoration of roads and public areas. The works are to be delivered as one contract, with tenders due by 3 November 2026. The contract includes indicative progress milestones: at least 20% physical progress by 25% of the contract period, 45% by 50%, 75% by 75%, 90% by 90%, and full completion, testing, operational handover and restoration by 100%. The economically most advantageous tender is selected on the basis of the best price-quality ratio: technical offer 80% and financial offer 20%.