Renovation of Tupuri School and Daycare Centre
Summary
The City of Salo is procuring the comprehensive renovation of Tupuri School and Daycare Centre at Taimistokatu 1. The works will be carried out in three phases while the school and daycare continue operating in the building and grounds. The daycare phase is due by 22 December 2027, the renovation of the old school section by 22 December 2028, and the new school section by 1 August 2029; the kitchen works are scheduled for 1 June–15 August 2028. The overall contract, including façade, roof and yard works, is due for completion by 3 December 2029.