Tender detail
Design and construction of the advanced cell therapy centre at Fundeni Clinical Institute
Summary
Fundeni Clinical Institute is procuring the design, construction and designer’s technical assistance for a new advanced cell therapy research and production centre, created by converting the existing C3 building in Bucharest. The contract also covers supplying, installing, commissioning and testing the medical and laboratory equipment needed to operate the facility, including cryogenic storage, cleanroom safety and monitoring systems, cell-processing and quality-control equipment, and microbiological testing equipment. The estimated value is RON 51,408,205.94 excluding VAT, and the contract duration is 19 months; the works carry a 60-month warranty period.
More tender information after sign-in
The public view shows key tender details. Sign in to open official links, documents and AI tender support.