The tender covers construction of the water supply network in Jasienica, Tłuszcz Municipality, divided into two lots: approximately 373 metres along Jagodowa Street and approximately 432.5 metres along Kościelna Street. The works also include all necessary ancillary works, commissioning, acceptance and handover of the network. The completion period is 63 days for each lot, and tenders may be submitted for both lots. The tender must be submitted electronically in Polish by 1 October 2026 at 09:00. The award criteria are price (60%), warranty period (20%) and the experience of the person responsible for performing the works (20%). Participation requires a site manager with the required professional authorisation.