Construction of well no. 3 at the water supply intake in Drzewica
Summary
The contract concerns construction of well no. 3 at the water supply intake in Drzewica, on plot no. 539. The well is to be drilled using the percussion method with an eccentric bit to a planned depth of 80 metres. The contractor must also prepare hydrogeological documentation after drilling and test pumping, prepare the project information sheet and obtain the environmental decision, and prepare the water-law report and obtain the water permit. The contract period is 6 months. Offers must be submitted electronically in Polish through the designated purchasing platform by 23 September 2026 at 11:00. Price is the only award criterion, weighted at 100%. No bid guarantee is required, but performance security is required.