The contract covers construction of a 608 m access road to the Miradz Forest Nursery, together with a manoeuvring and parking area with 10 spaces in the Miradz forest district. The works include earthworks, road sub-base and asphalt surfacing, road markings, traffic organisation and as-built surveying documentation. The contract must be completed within 50 days of handover of the construction site, which is to take place within 5 days of contract signature. Offers must be submitted electronically by 10 September 2026 at 10:00. Price carries 60% of the score and the warranty period carries 40%; 60 months gives 0 points, 72 months 20 points and 84 months 40 points. A PLN 5,000 bid guarantee is required.