Expansion of the Lipiny Water Treatment Plant by Installing an Additional Water Tank
Summary
The procurement concerns construction works to expand the Lipiny water treatment plant by installing an additional 100 m³ potable-water storage tank. The works include external process pipelines, a power cable for the tank, removal of a conflicting section of fencing and construction of new fencing around the tank. The contract period is 60 days. Bids must be submitted electronically by 9 September 2026 at 10:00. Offers are scored on price (60%) and warranty period (40%). The contractor must provide performance security and comply with the employment-on-the-basis-of-an-employment-relationship requirement for the activities covered by the notice.