Construction of the road link between Murowianka Street and Krasińskiego Street
Summary
The contract covers construction and expansion of a road link in Bochnia between Murowianka Street and Krasińskiego Street. The works include temporary traffic management, demolition and road construction, curbs and edging, asphalt carriageway, paved sidewalks and access connections, road signs, stormwater drainage, and works on low-voltage electricity, gas and water networks. The works must be completed within 70 days of signing the contract. Offers must be submitted electronically by 2 September 2026 at 10:00, in Polish, using the required forms and electronic signature. The award criteria are price (60%) and warranty period (40%). No bid guarantee is required, but a performance guarantee equal to 5% of the total gross tender price is required.