Repair of the Saldaña wastewater treatment plant and rehabilitation of sewer collectors
Summary
SOMACYL is procuring repairs to the wastewater treatment plant in Saldaña, Palencia, and works to repair and waterproof the municipality’s sewer collectors. The scope includes interventions on several collector sections and treatment-plant equipment, as well as commissioning the facility. The procurement is a single integrated lot; the works are scheduled for 4 months and the commissioning service for 6 months from acceptance of the works. The total estimated budget including VAT is EUR 229,064.20.