Tender detail

Heat export from Dukovany to Brno: plant-room equipment and external connecting pipeline

Summary

ČEZ is procuring the design, supply, installation and commissioning of the mechanical and process equipment for a heat-export plant room and its external connecting pipeline at the Dukovany Nuclear Power Plant. The scope includes pipeline connections and pre-insulated pipes, valves and supporting steel structures, heat exchangers, a thermal deaeration tank, circulation and other pumps, and equipment for chemical dosing. The contract is divided into one lot.

Reference number
791153-2026
Buyer
ČEZ, a. s.
Country
Czechia (CZE)
Procedure
Competitive procedure with negotiation
CPV
45231112 Installation of pipe system
Deadline
2026-12-21
Status
Open
Contract subject
Works
Estimated value
Not published
Source
TED

More tender information after sign-in

The public view shows key tender details. Sign in to open official links, documents and AI tender support.