Tender detail
Renewal of secondary equipment and upgrade of protection and information systems at Horná Ždaňa substation – engineering and design services
Summary
Slovenská elektrizačná prenosová sústava is procuring engineering and design services for the renewal of 110 kV and 400 kV secondary equipment, 110 kV ROP and the upgrade of the 400 kV RIS at Horná Ždaňa substation. The single-lot contract includes project documentation for selecting and delivering the works, a works schedule, as-built documentation, design supervision during commissioning and trial operation, a fire-safety design, and preparation and coordination of a construction health and safety plan. The planned contract period is 55 months.
More tender information after sign-in
The public view shows key tender details. Sign in to open official links, documents and AI tender support.