Tender detail
Phase 1 of the I/45 road realignment between Nové Heřminovy and Zátor
Summary
The tender covers Phase 1 of the realignment of road I/45 between Nové Heřminovy and Zátor. The works comprise approximately 5 km of new road, junctions and roundabouts, bridges, retaining walls, noise barriers, and the realignment and connection of lower-class roads affected by the project. The estimated value is CZK 2,433,000,000, and the planned contract duration is 47 months. Bids will be assessed on price (90%) and warranty period (10%); a lower price and longer warranty period receive a better score. A bid guarantee of CZK 15,000,000 is required, and bids must remain valid for 10 months. Precise qualification and compliance requirements must be checked in the tender documents.