EEM – Empresa de Electricidade da Madeira is procuring construction and installation works to establish and adapt its new logistics centre beside the Ponte Vermelha substation in Ribeira Brava. The single-lot contract includes a two-level support structure for four containers with access stairs and platform and utility connections; storage platforms for wooden poles and cable drums; perimeter fencing; an administrative container and cable-drum storage system; and collection and land and sea transport of existing containers from Porto Santo. The works are to be completed within 120 days, with a base price of EUR 115,000 excluding VAT.