Tender detail
Upgrade of the Fire Protection Network at Vitória Thermal Power Plant
Summary
EEM – Empresa de Electricidade da Madeira is procuring works to upgrade the existing fire-protection network at Vitória Thermal Power Plant in Funchal, Madeira. The single-lot project includes replacement and installation of pipework, pumps and a supplementary water tank, foam and fire-extinguishing equipment, sprinklers, electrical and monitoring systems, and associated civil works. Testing, commissioning and staff training are included. The estimated maximum price is EUR 2,400,000 excluding VAT, and the works are to be completed within 550 days.