Design, supply and installation of a containerised water treatment plant in Drawno
Summary
The Municipality of Drawno is procuring the design, supply and installation of a complete containerised water treatment plant with associated infrastructure on plot 110/4 at Kwiatowa 3. The single, undivided contract covers design and approvals, site investigations, earthworks and foundations, the plant container, internal and external installations, utility connections and site works, followed by documentation and approvals for the permanent facility. The first phase is due by 20 December 2026 and the second by 30 June 2027. Alarm and monitoring systems specified in the functional programme are excluded from the installation.