Reconstruction and adaptation of basement rooms in Łąck Primary School into a Temporary Shelter
Summary
The contract covers the reconstruction and adaptation of basement rooms in the Primary School building in Łąck into a Temporary Shelter. The works include rebuilding the bathroom and façade, partially bricking up window openings, constructing window partitions, creating a doorway and installing an EI30-rated door, replacing window joinery, and supplying construction props to reinforce the ceilings. The contract period is 70 days. Bids must be submitted electronically in Polish by 1 September 2026 at 10:00. The bid must be secured with a PLN 4,000 tender guarantee. Evaluation is based on price (60%) and warranty (40%).