Renewal of the Sant Ignasi transformer substation on the Núria rack railway
Summary
Ferrocarrils de la Generalitat de Catalunya is procuring, in one lot, works to renew the Sant Ignasi transformer substation on the Núria rack railway, at Queralbs. The works include replacing 630 kVA and 400 kVA transformers, installing medium-voltage connectors and a new control cabinet with control and signalling cabling, and removing and disposing of equipment taken out of service. The tender budget is €108,501.93 excluding VAT.