Tender detail
Occupational safety specialist for the Biblis nuclear power plant project
Summary
EWN Entsorgungswerk für Nuklearanlagen GmbH is procuring occupational safety specialist services for the dismantling of the reactor pressure vessel internals in Blocks A and B of the Biblis Nuclear Power Plant. The anticipated service period is from 1 January 2027 to 31 March 2028, with an optional extension through 31 December 2028. The estimated scope includes 12 site visits in 2027 and 3 in the first quarter of 2028, plus an option for 9 further visits; other services are estimated at 40 hours in 2027, 10 hours in the first quarter of 2028 and an optional 30 hours thereafter. One visit per year is also anticipated at the Rubenow facility in 2027 and 2028.
More tender information after sign-in
The public view shows key tender details. Sign in to open official links, documents and AI tender support.