Tender detail
Repair of the Grünauer Allee III R 9 Bridge
Summary
The City of Leipzig is procuring repair works for the bridge at Grünauer Allee III R 9. The works include renewing 780 m² of asphalt and waterproofing, replacing 50 m of bridge transition structure, erecting 5,000 m³ of scaffolding, demolishing 40 m³ of concrete, installing 50 m³ of precast concrete, restoring 370 m of railings and electrical protection, repairing 1,700 m² of concrete, and renewing lighting on eight masts. The works are scheduled from 5 April to 24 September 2027; the contract is not divided into lots.