Construction of the Gdynia Chylonia integrated transport hub – Stage II North – Part II
Summary
The contract concerns construction works for the Gdynia Chylonia integrated transport hub, including demolition works, temporary access, a tunnel exit with stairs and a ramp for persons with disabilities, a social building for city transport drivers, a stop platform, canopies, pavements, small architecture, greenery, retaining walls, drainage, lighting, cable network works and information boards. The contractor must complete the works within 26 weeks from contract signature and then hand over the occupancy permit or effective completion notice 7 weeks later. The bid must be submitted electronically in Polish, with a bid security of PLN 40,000, and the contractor must provide performance security, insurance, relevant personnel and evidence of prior experience.